IOS – Delta AC coupled battery with/without Delta Solar inverter)

Estimated time to commission and connect: Less than 5 minutes

  • Step 1. Type in your installer email address and password.
  • Step 2. Press Sign-in and Commission (bottom right button)
  • Step 3. Press either the “QR Code” or “Type-In” button. After scanning or typing in a serial number it will appear below the relevant title. When you have finished scanning the devices onsite press “SET”.
  • Note: If you press the QR code scanner you can scan the QR code found on the side of the inverter or battery system. Please remember to scan the QR code found next to the serial number on the device. If you cannot find this or scan it you may type in the serial number manually using the “Type-In” button.
  • Note: When typing in the serial number remember to take note of the letter “O” found at the beginning of many serial numbers, not the number “0”.
  • Note: If you have a Data Collector please go to the data collector setup procedure.

  • Step 4. Select the ID’s of each inverter and press “SET”.
  • Note: If you selected multiple inverters on the previous page, press the “Auto” button to automatically allocate ID’s amongst the selected inverters. This example only contains one device.

  • Step 5. Select the country and Select the Grid code. Press “SET” to continue
  • Note: The Grid code selection list has multiple DNSP’s in Australia. When selected these will have settings tailored to their technical specifications.

  • Note: See list of some available grid codes you will find in the list. AU_WP = Western Power. (Screenshot taken from Android)
  • Note: After pressing “SET” you will notice there is an advanced tab. Press “NEXT” to continue. To see what is inside the advanced tab see next image.
  • Note: Type in the service code: 4613.
  • Note: You are able to specifically adjust grid settings, dry contact and DRM in the advanced tab. When commissioning a Delta Solar inverter more options will appear such as export control.
  • Step 6. After pressing “NEXT you will be taken to the VSG/ATS Settings.
  • VSG Function: OFF/ON –
    • Turn “ON” for Application 5 Use Only (multiple BX6.3)
    • Turn “OFF” for all other applications
  • Backup Power Type: Internal ATS/External ATS.
    • Internal ATS: Application 1, 2 and 3.
    • External ATS: Application 4 and 5.
  • To see how these applications are configured please see the manual: https://support.delta-es.com.au/wp-con…
  • Once the correct options have been selected press “SAVE” if you only have 1x Battery then press “NEXT”.
  • If you have multiple BX6.3 master batteries press “MULTIPLE SET” to set all ID’s to those settings. Then press “NEXT”.

  • Step 7. Battery Configuration
  • Selecting your battery type:
    • If you have a BX6.3 (master battery) please select BX6.3 as the battery type. If you have a BX6.3 and an EX (extension slave battery ~half the size of the BX6.3) then please select BX12.6.
  • Select the time schedule for the SOH cycle, as mentioned in the red text below the “SAVE” button it will cycle the battery once a year.
  • Step 8. Change the password of the inverter to a desired password.
  • Note: In the next step if you chose to connect to the cloud, the password will change when you perform the final connection to the cloud. .
  • Note: You cannot change the password to “DELTASOL” as it is the default password.
  • Note: Press “Connect to the Cloud” to complete the cloud connection. Press skip if the system is going to be offline (not internet connected).
  • Step 9. Select Wi-Fi tickbox. Then select the end-customers home Wi-Fi router SSID (Wi-Fi Name). Type in the password of the router.
  • Then press “SET”
  • Note: If the end-customers Wi-Fi did not show up press the scan button again.
  • Note: See the – XX dBm next to the Wi-Fi router. If the signal strength is weaker than -70dBm the connection may not be stable enough for connection.
  • Step 10. Select “New Plant”, select a plant type and type in a plant name.
  • Note: The plant name must be unique.
  • Note: You can the “Add device to my plant” is when you are adding another Delta device to an existing plant.
  • Note: Plant Type Selection
    • -Feed-in Without Power meter: H5A_222 without CT clamp
    • -Feed-in With Power meter: H5A_222 with CT clamp
    • -Battery storage with Power meter: Delta AC Coupled battery (BX6.3/BX12.6) with/without Inverter. CT clamp must be attached to BX6.3.
  • Step 11. As an installer typically you have already created an account for the end-customer. At this point click “Assign to” and type in the end-customers email address.
  • Note: This will allow you to fleet monitor all the plants you set up and the end customer will be able to see there own solar monitoring.
  • Note: When the setup is completed you will see the success message show up.

Congratulations, you have setup your Delta device(s)!