Below is a table providing the current stance from DNSP’s required default PQ settings:
Network |
Default power quality setting |
Western Power |
Australia B |
Horizon Power, TasNetworks |
Australia C |
All other Australian networks |
Australia A |
(16/12/2021) – Find some helpful quick links for some DNSP’s technical requirements relating to grid code selection. Please note the links are simply a guide, please ensure you are getting the latest information from the DNSP.
- Western Power – Basic Embedded Generator (EG) Connection Technical Requirements – 25 November 2021
- Horizon Power – Basic EG Connection Technical Requirements – 14 December 2021
- Ergon/Energex – Statement on AS4777.2:2020 changes – STNW1170 Connection Standard for Micro EG Units – 1 July 2020
- SAPN – Technical Standard – TS129 – 6 July 2021
- TasNetworks – Basic Micro Embedded Generation Connection Technical Requirements – September 2021